Case study:
Marks & Spencer
Workplace Consultancy
Commercial Fit-Out
Office Refurbishment
Design Development
Space Planning
Project Management
Client
Marks & Spencer
Value
£9.4 million
Construction
48 weeks
Area
25,500 sq ft
Head Office refurbishment with emphasis on Wellbeing.
The brief – to maximise occupancy to integrate staff and personnel from lease end adjacent building.
Working in a live building with end of life infrastructure
5 phases with churn moves over ten floors
New Mechanical and Electrical services
New Tea Points incorporating Collaboration and Break out facilities
Tight work programme to meet lease expiry on adjacent building




Previous Project
Next Project